Mix ratio M20: 1 : 1.5 : 3 (cement : sand : aggregate)W/C = 0.5
How the Concrete Mix Ratio Calculator Works
The calculator uses IS 456:2000 nominal mix proportions. For a given grade and volume, it computes dry material quantities using a dry volume factor of 1.54 (wet concrete shrinks ~35% when cured), cement density of 1440 kg/m³, and the water-cement ratio for each grade. Formula: Dry volume = Volume × 1.54, then each material is proportioned by the C:S:A ratio.
Concrete Grade Reference Table
| Grade | Ratio (C:S:A) | Strength (MPa) | Typical Use |
|---|---|---|---|
| M10 | 1:3:6 | 10 | Lean mix, blinding concrete |
| M15 | 1:2:4 | 15 | Mass concrete, unreinforced |
| M20 | 1:1.5:3 | 20 | RCC slabs, beams, columns |
| M25 | 1:1:2 | 25 | Bridges, heavy structures |
| M30 | Design mix | 30 | High-rise, pre-stressed |
Worked Examples
- Slab 5m × 4m × 0.15m = 3 m³, Grade M20 (1:1.5:3): Dry volume = 3 × 1.54 = 4.62 m³. Cement = 4.62 × (1/5.5) × 1440 = 1210 kg. Sand = 4.62 × (1.5/5.5) = 1.26 m³. Aggregate = 4.62 × (3/5.5) = 2.52 m³.
- Footing 1 m³, Grade M15: Dry volume = 1.54 m³. Ratio 1:2:4 (sum=7). Cement = 1.54/7 × 1440 = 317 kg (7 bags of 50 kg). Sand = 0.44 m³. Aggregate = 0.88 m³.
- Driveway slab 10 m³, Grade M25: Dry volume = 15.4 m³. Ratio 1:1:2 (sum=4). Cement = 15.4/4 × 1440 = 5544 kg (111 bags). Order ready-mix at M25 grade.
Frequently Asked Questions
- What is the most common concrete mix ratio for slabs?
- M20 (1:1.5:3) is the standard for reinforced concrete slabs, beams, and columns. It achieves 20 MPa at 28 days, which meets minimum structural requirements in most residential codes.
- How much cement do I need per m³ of M20 concrete?
- Approximately 403 kg of cement (about 8 bags of 50 kg) per m³ of M20 concrete, using a 1:1.5:3 ratio with a dry volume factor of 1.54.
- What does the water-cement (W/C) ratio mean?
- The W/C ratio is the mass of water divided by the mass of cement. Lower W/C (e.g., 0.45) gives stronger, denser concrete but is harder to place. Higher W/C (0.60) is workable but weaker. M20 uses W/C = 0.55.
- Can I use this for M30 and above?
- M30 and above are design mixes — the ratio is determined by trial batching and laboratory testing, not nominal proportions. Use this calculator for M10 to M25 only. For M30+, consult a structural engineer.