Excavation Volume Calculator

Calculate excavation volume in bank measure and loose measure for truck haulage.

Advertisement

Bank Measure vs Loose Measure

Bank measure (BCM) is the volume of soil in its natural, undisturbed state — this is the volume you need to remove. Loose measure (LCM) is what the excavated soil fills when loaded into trucks — it is larger because digging breaks up the soil structure, adding air voids (swell). Loose volume = Bank volume × (1 + swell factor).

Swell Factor Guide

Soil TypeSwell FactorExample
Rock / gravel10%Fills truck with 10% more volume than bank
Sandy soil20%Typical sand or loam
Common earth25%Mixed soil, topsoil
Clay / wet soil35%Heavy clay expands most when broken up

Worked Examples

  • Basement pit 8m × 6m × 2m, common earth (25% swell): Bank = 96 m³. Loose = 96 × 1.25 = 120 m³. Truck loads (5 m³ trucks) = 24.
  • Trench 20m × 0.6m × 1.5m, clay (35% swell): Bank = 18 m³. Loose = 18 × 1.35 = 24.3 m³. Truck loads = 5.
  • Pool excavation 10m × 5m × 2m, sandy soil (20% swell): Bank = 100 m³. Loose = 120 m³. Truck loads = 24.

Frequently Asked Questions

How many truck loads to remove 100 m³ of soil?
A standard 5 m³ tipper holds 5 m³ of loose soil. For 100 m³ bank of common earth (25% swell) = 125 m³ loose. At 5 m³ per truck: 25 truck loads. For a 10 m³ truck, 13 loads.
What is the difference between excavation and earthwork?
Excavation refers to cutting below ground level, typically for foundations, basements, or utilities. Earthwork is the broader term covering all bulk movement of soil — excavation, embankment, grading, and compaction.